| Foundation Termite Proofing | Anti-termite will be used in foundation side walls and after sand filling | |
| Brick | Awal | Awal A+ (Rs.18-20/brick) |
| Sand | Ravi sand | |
| Cement | Bestway / Maple leaf | Chunai ratio 1:5 , Plaster 1:4 (DPC-Beams PCC 1:4:8) (RCC Slab 6” 1:2:4) |
| Crush | Sargodha Plant | 3’’’-4’’’ plant crush will be used throughout @160/cft |
| Water Proofing | Multiple levels (Beveled Edge) | Terrazzo in septic tank, UGWT & Sewerage junction, Membrane Sheet on DPC, 1.5mm, Cement based Waterproof Chemical will be used on dead-walls, washrooms & as per requirement. |
| Steel | G-60 Stamped | Mughal, Model, Aziz, Kohenoor, FF (Rs. 230/kg) |
| Shuttering | Steel plates | For all RCC work |
| 2nd-Termite treatment | Before floor leveling (Kacha) | Anti-termite pipes in ground floor will be installed. |
| Door Frames | 16 gauge Jist Chadar | Up to 8 feet height |
| Safety Grills | Multiple designs to choose from (16 + 18 gauge combination) | Any design except CNC & wrought Iron |
| Main Gate | Multiple designs to choose from (16 + 18 gauge combination) | Variety of designs to choose from, wrought Iron (Dhalai), Total CNC extra will be charged |
| Electric Pipes | GM | GM Pipe will be used. |
| PPRC / UPVC | Popular / GM | Both are recommended. PN16 PPRC will be used with 32mm. Mainline will be concealed with concrete Medium grade pipes will be used. |
| Water Tank | 750Ltr for 5 Marla, 1000Ltr for 10 Marla, food grade water tank will be used (Included) | For concrete tank, it will be charged extra |
| Installment | Description | % | Amount |
| Advance | Before Excavation | 20 | 1,200,000 |
| 1st | DPC level | 10 | 600,000 |
| 2nd | Door Frame Installation 7 feet chanai | 6 | 360,000 |
| 3rd | 1st Lenter | 12 | 720,000 |
| 4th | Door Frame Installation 7 feet chanai | 6 | 360,000 |
| 5th | 2nd lenter | 12 | 720,000 |
| 6th | Mumty & Boundary walls & parapet wall | 10 | 600,000 |
| 7th | PPRC / UPVC / Wall Piping / Inner Plasters | 10 | 600,000 |
| 8th | Outer Plasters Water Tank Septic Tank | 4 | 240,000 |
| 9th | Floor Leveling kachay | 4 | 240,000 |
| 10th | Kitchen Slabs, wardrobe bases, Safety Grills, Main Gate | 4 | 240,000 |
| 11th | final Payment | 2 | 120,000 |
| GRAND TOTAL | 6,000,000 | ||
| Rate | Area | Total Amount |
| 3000 | 2000 | 6,000,000/- |
| >>>>> | >>>>>>>> | 6,000,000/- |
| If Plot is deeper then 3ft Extra will be charged | ||