| Foundation Termite Proofing | Anti-termite will be used in foundation side walls and after sand filling | |
| Brick | Awal | Awal A+ (Rs.23-24/brick) |
| Sand | Ravi sand | |
| Cement | Bestway / Maple leaf | Chunai ratio 1:5 , Plaster 1:4 (DPC-Beams PCC 1:4:8) (RCC Slab 6” 1:2:4) ( @ 1550 ) |
| Crush | Sargodha Plant | 3’’’-4’’’ plant crush will be used throughout @185/cft |
| Water Proofing | Multiple levels (Beveled Edge) | Terrazzo in septic tank, UGWT & Sewerage junction, Membrane Sheet on DPC, 1.5mm, Cement based Waterproof Chemical will be used on dead-walls, washrooms & as per requirement. |
| Steel | G-60 Stamped | Mughal, Model, Aziz, Kohenoor, FF (Rs. 255/kg) |
| Shuttering | Steel plates | For all RCC work |
| 2nd-Termite treatment | Before floor leveling (Kacha) | Anti-termite pipes in ground floor will be installed. |
| Door Frames | 16 gauge Jist Chadar | Up to 8 feet height |
| Safety Grills | Multiple designs to choose from (16 + 18 gauge combination) | Any design except CNC & wrought Iron |
| Main Gate | Multiple designs to choose from (16 + 18 gauge combination) | Variety of designs to choose from, wrought Iron (Dhalai), Total CNC extra will be charged |
| Electric Pipes | GM | GM Pipe will be used. For PPRC AC Drains additional @ Rs.3500/-per point. |
| PPRC / UPVC | Popular / GM | Both are recommended. PN16 PPRC will be used with 32mm. Mainline will be concealed with concrete Medium grade pipes will be used. |
| Water Tank | 750Ltr for 5 Marla, 1000Ltr for 10 Marla, food grade water tank will be used (Included) | For concrete tank, it will be charged extra |
| Installment | Description | % | 03 Marla Amount | 05 Marla Amount | 08 Marla Amount | 10 Marla Amount | 01 Kanal Amount |
| Advance | At the Time of Signing Contract | 10 | 487,500 | 650,000 | 1,040,000 | 1,137,500 | 2,112,500 |
| Advance | Before Excavation | 20 | 975,000 | 1,300,000 | 2,080,000 | 2,275,000 | 4,225,000 |
| 1st | DPC level | 10 | 487,500 | 650,000 | 1,040,000 | 1,137,500 | 2,112,500 |
| 2nd | Door Frame Installation 7 feet chanai | 6 | 292,500 | 390,000 | 624,000 | 682,500 | 1,267,500 |
| 3rd | 1st lenter | 12 | 585,000 | 780,000 | 1,248,000 | 1,365,000 | 2,535,000 |
| 4th | Door Frame Installation 7 feet chanai | 6 | 292,500 | 390,000 | 624,000 | 682,500 | 1,267,500 |
| 5th | 2nd lenter | 12 | 585,000 | 780,000 | 1,248,000 | 1,365,000 | 2,535,000 |
| 6th | Mumty & Boundary walls & parapet wall | 5 | 243,750 | 325,000 | 520,000 | 568,750 | 1,056,250 |
| 7th | PPRC / UPVC / Wall Piping / Inner Plasters | 5 | 243,750 | 325,000 | 520,000 | 568,750 | 1,056,250 |
| 8th | Outer Plasters Water Tank Septic Tank | 4 | 195,000 | 260,000 | 416,000 | 455,000 | 845,000 |
| 9th | Floor Leveling kachay | 4 | 195,000 | 260,000 | 416,000 | 455,000 | 845,000 |
| 10th | Kitchen Slabs, wardrobe bases, Safety Grills, Main Gate | 4 | 195,000 | 260,000 | 416,000 | 455,000 | 845,000 |
| 11th | final Payment | 2 | 97,500 | 130,000 | 208,000 | 227,500 | 422,500 |
| GRAND TOTAL | 100 | 4,875,000 | 6,500,000 | 10,400,000 | 11,375,000 | 21,125,000 | |